How long does a Bathroom Renovation really take?

Pre-Construction Stage

1. UNDERSTANDING THE PROJECT ( 1 – 4 weeks ) 

It is important to have an understanding of what you are after in terms of your renovation, so that you can find a contractor who aligns well with what you are trying to achieve. Going in with a solid plan on layout + general vibe of materials and products will make the discussion and planning process of your renovation far more efficient. 

 
 2. Find the Right Renovation Company  ( 1 – 4 weeks ) 

It is incredibly important to look around and find a company that really represents you and your style! A lot of renovation companies specialise in a specific look or atmosphere so find someone who aligns with yours. Are you looking for a Full or Partial Renovation? This is important to note as a few companies don’t actually offer partial renovation services. 

 3. Sign Contracts and Finalise construction Schedules.  ( 1 week ) 
Once you have decided on a contractor that best fits you, they will have a contract put together for you to Sign before construction commences. The contract will comprise of information regarding The work that needs to be done, An estimate timeline for completion and timing of payments throughout project. Make sure to read through this contract thouroughly and look out for any fineprint that you must be aware of. 
 
 4. Obtain Permits and Approvals (Ranges widely depending on which approvals you need for this project, be prepared and allow for weeks – months) 

Obtaining Permits and Approvals will be the one place where problems can occur. If you are renovating an apartment room or spaces that aren’t stand alone houses, you need to attain board approval. This alone can take a few months! 

 
 5. Source Materials (Wide range, prepare in advance for weeks) 
If you are responsible for sourcing all the materials, then make sure to place orders as soon as the design plan has been completed! Shopping for features to include in your bathroom can be a very enjoyable and exciting experience. However in saying this, it won’t be fun having to delay construction time because one of your features (eg. Toilet, bath, shower) hasn’t been delivered on time. Here at Lukes Renovations  we supply everything you need in a bathroom, from toilet paper dispensers to Luxurious Hovering Vanities. 

Construction Stage

 1. Demolition ( 1 day ) 
It is demolition time!! Now that all the paperwork is done, it is finally time to start creating the bathroom of your dreams! Depending on the size of your bathroom and the intricacies on what you want to keep and what you want to do, this process shouldn’t take for than 4 hours 🙂 
 
 2. Reroute plumbing and Electrical ( 1- 3 days ) 
By this stage, your bathroom should be stripped completely and it is time to reroute plumbing and electrical, which can take anywhere between 1-3 days depending on the amount of work that needs to be completed on origional  framework. 
 

 3. Wall prep and waterproof (2-3 days)

All the walls must be prepared well for the waterproofing and tiling. Crucial stage that not only effects the finish product, but also the longevity of the bathroom.

4. Tiling

Depending on the size of your space, the format and size of the tile, laying down the floor tiles and wall tiles can take 1-4 days.

5. Installation complete ( 1- 3 days ) 

Now that the foundation and floor have been set up, it is now time to start piecing your oasis together! This stage is where all shower, bath, toilet, accessory, tile, lighting and shelving fittings will be completed. You should expect this process to take 1-3 days give or take. 

 5. Clean Up Day (1 day) 
Contracts state that the space be left in “broom swept” condition, however we highly recommend hiring a cleaner to thoroughly clean the space! This way, when you first use your bathroom it is in immaculate condition and you have nothing to do… but relax!

Post-Construction Stage

 Final walk through with contractors ( 30 mins ) 
After spending all this time and money on renovating your new bathroom, you want to make sure everything is working perfectly! 
 
We will ensure everything is ready for handover.

And there you have it!! The ultimate time guideline to your next bathroom renovation! 

We aim to complete all our standard bathroom renovations within 2 weeks!